Reading: Chennai Metro Rail’s TBMs to begin tunneling between Thiruvanmiyur and Indira Nagar for phase II project in November
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Chennai Metro Rail’s TBMs to begin tunneling between Thiruvanmiyur and Indira Nagar for phase II project in November

India News

Chennai Metro Rail’s TBMs to begin tunneling between Thiruvanmiyur and Indira Nagar for phase II project in November

India Times Now Desk
Last updated: October 5, 2025 7:31 am
India Times Now Desk
Published: October 5, 2025
Share
SHARE


Tunneling is all set to commence at Thiruvanmiyur for Chennai Metro Rail’s phase II project.

Tunneling is all set to commence at Thiruvanmiyur for Chennai Metro Rail’s phase II project.
| Photo Credit: Ragu R

Chennai Metro Rail is all set to start tunnelling work in one of the most challenging stretches for the upcoming phase II project between Thiruvanmiyur and Indira Nagar in November.

Two tunnel boring machines (TBM) will create twin tunnels for a distance of nearly 650 metres between Thiruvanmiyur and Indira Nagar.

In the 118.9 km phase II project, corridor 3 from Madhavaram to SIPCOT via Adyar whose length is 45.8 km has a significant portion of underground network of 26.8 km; one of them is the Thiruvanmiyur to Indira Nagar stretch. In a few years, trains originating from Madhavaram will take commuters through at least 40 locations including Thiruvanmiyur and Indira Nagar before reaching SIPCOT.

Officials of Chennai Metro Rail Limited (CMRL)said they have been excavating for a few weeks now at Thiruvanmiyur station site; while one of the TBMs have been lowered, the other will be done soon. 

The major challenge now is excavation of the site due to the presence of hard rock. “We did expect to encounter hard rock at Thiruvanmiyur but didn’t foresee that it would be such high-quality hard rock like granite. Initially, the contractor planned to carry out controlled blasting to break them and complete the excavation. But as a better alternative, the contractor chose to use chemicals and disintegrate the hard rock,” an official said.

CMRL officials added they are currently excavating at a depth of 22 metres at Thiruvanmiyur. Owing to the presence of hard rock, the tunnelling work too may be quite slow in this 650-metre stretch between Thiruvanmiyur and Indira Nagar. Ideally such a short stretch can be completed soon, but officials expect that it may take nearly a year for the machines to create twin tunnels. 

“If the machine constantly drills through hard rock, the cutter head discs of the TBM will wear out soon and we will have to carry out a process called cutterhead intervention and change the parts. Cutterhead intervention may have to be done several times for both machines along this stretch and could be time consuming,” an official said.

Published – October 05, 2025 01:01 pm IST



Source link

Where does the India-U.S. trade deal stand? | Explained
‘Mann Ki Baat’: PM Narendra Modi makes special mention of traditional metal craftsmanship of Karimnagar
PM Modi hails India-Seychelles ties as ‘steady, strong and long-lasting’
The Hindu EducationPlus fair: ‘Career counselling inspires confidence, eases course anxiety’
DSEL issues order to increase egg distribution coverage in Karnataka schools to 90%
TAGGED:Chennai Metro Rail’s TBMsChennai metro tunneling workThiruvanmiyur and Indira Nagar
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

Telangana Deputy Chief Minister Bhatti Vikramarka’s CPRO Madhusudhan passes away

India Times Now Desk
India Times Now Desk
April 27, 2026
Ganderbal encounter: Jammu & Kashmir L-G Manoj Sinha orders magisterial inquiry
Who is Mahira Sharma, Bigg Boss 13 fame, who was recently spotted with cricketer Mohammed Siraj?
Concern over exclusion of eye treatment package from Medisep 2
Stock under Rs 50 ends in green even as benchmark indices ended over 1% lower, check details
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?