By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
India Times NowIndia Times NowIndia Times Now
Notification Show More
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Reading: Supreme Court to take a fresh look at pleas on ex post facto eco clearance regime
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Supreme Court to take a fresh look at pleas on ex post facto eco clearance regime

India News

Supreme Court to take a fresh look at pleas on ex post facto eco clearance regime

India Times Now Desk
Last updated: February 16, 2026 8:31 pm
India Times Now Desk
Published: February 16, 2026
Share
SHARE


A three-judge Bench of the Supreme Court decided to take a fresh look at writ petitions and appeals concerning ex post facto environmental clearance of construction and public projects across the country.

A three-judge Bench of the Supreme Court decided to take a fresh look at writ petitions and appeals concerning ex post facto environmental clearance of construction and public projects across the country.
| Photo Credit: Sushil Kumar Verma

A three-judge Bench of the Supreme Court on Monday (February 16, 2026) decided to take a fresh look at writ petitions and appeals concerning ex post facto environmental clearance of construction and public projects across the country.

The Bench headed by Chief Justice of India (CJI) Surya Kant scheduled the case for detailed hearing on February 25. The CJI said the court would not tolerate any adjournments on that day.

A Division Bench of the Supreme Court had struck down the Centre’s grant of ex post facto or retrospective environmental clearances (ECs) as a “gross illegality” and an “anathema” in a judgment on May 16, 2025.

However, a subsequent three-judge Bench of the court had recalled the May 16 judgment in a majority verdict delivered in November 2025.

The majority opinion for the three-judge Bench authored by Chief Justice (now retired) B.R. Gavai had concluded that the continued operation of the May 16 judgment would have a “devastating effect” and “thousands of crores of rupees” invested in building and infrastructure projects would “go to waste”. Justice K. Vinod Chandran had backed his view, forming the majority on the Bench.

Justice Ujjal Bhuyan, the third member of the Bench, had however recorded a sharp dissent. He had termed the majority view as an “innocent expression of opinion” which overlooked the “very fundamentals of environmental jurisprudence”.

The majority opinion of Chief Justice Gavai and Justice Chandran had, while recalling the May 16 judgment, ordered the writ petitions, including the lead plea by NGO Vanashakti, to be “restored to file”.

On Monday, petitioners, led by senior advocates Sanjay Parikh and Gopal Sankaranarayanan, argued that the majority opinion of November 2025 authored by Justice Gavai had only recalled the May 2025 judgment without expressly giving an authoritative finding on the validity of the two Office Memorandums (OMs) of 2017 and 2021, which had formed the bedrock on which the government had worked the ex-post facto environmental clearance regime.

The majority judgment in November 2025 had recorded that the Division Bench which struck down the OMs did not have the benefit of several judicial precedents before pronouncing their verdict on May 16.

Solicitor General Tushar Mehta, appearing for the Steel Authority of India, submitted that the May 2025 had put several significant public projects on hold, including an airport in Karnataka.

Senior advocate P. Wilson and Tamil Nadu Advocate General P.S. Raman submitted that a 218-crore cancer hospital project in the State and the construction of a District Collectorate office had been halted abruptly as an aftermath of the May 2025 judgment.

Published – February 16, 2026 09:39 pm IST



Source link

Cab driver assaulted on KH Road
ED raids in Maharashtra, Gujarat in Salim Dola drugs case
Sukhu inaugurates Shimla helicopter services, targets BJP over ₹1,000 crore waste
West Bengal election results: Find out who is winning from your constituency
A.P. Discoms told to ensure uninterrupted power supply during Sivaratri festival
TAGGED:chief justice of indiaenvironmental clearance cases hearing on February 25SC set hearings on February 25SC to review ex post factor environmental clearance casesSupreme Court of India
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

10 sentenced to life imprisonment for murder of panchayat president in Cuddalore in 2020

India Times Now Desk
India Times Now Desk
November 12, 2025
Cockroach imagery on conference poster ignites controversy at MG University in Kerala
VVITU hosts seminar on intellectual property rights
Homebuyers duped: ED attaches land parcels worth ₹585 crore in Haryana, Uttar Pradesh
UTF calls for strengthening government schools through increased enrolment
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?