Reading: Keralam to join hands with NTPC to set up 2,000-MW battery energy storage system at Kayamkulam
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Keralam to join hands with NTPC to set up 2,000-MW battery energy storage system at Kayamkulam

India News

Keralam to join hands with NTPC to set up 2,000-MW battery energy storage system at Kayamkulam

India Times Now Desk
Last updated: October 7, 2026 5:40 am
India Times Now Desk
Published: October 7, 2026
Share
SHARE


file image

file image
| Photo Credit: The Hindu

The Keralam government will establish a 2,000 megawatt hour (MWh) battery energy storage system (BESS) at Kayamkulam in Alappuzha district in collaboration with NTPC Ltd as part of addressing the electricity shortage faced by the State, according to Chief Minister V.D. Satheesan.

Keralam has also asked NTPC Ltd to develop a dedicated power plant for the State for long-term energy security.

For establishing the BESS, State-run Kerala State Electricity Board (KSEB) will ink a memorandum of understanding with NTPC Ltd and NTPC Green Energy Limited (NGEL). Mr. Satheesan said on Wednesday the decision was taken at a meeting he held with senior officials of NTPC Ltd in New Delhi. Electricity Minister Sunny Joseph also was present.

The BESS facility is expected to come up on NTPC land where the currently unused Rajiv Gandhi Combined Cycle Power Plant (RGCCPP) is situated.

It was also decided at the meeting to speed up work on a 27-MW solar power project implemented by NTPC at Kayamkulam.

Further, NTPC Ltd has agreed to supply 300 MW to Keralam from the NTPC project at Sinnar in Maharashtra, according to the Chief Minister. The supply will be at the rate of ₹5.18 per unit.

The Centre’s public sector unit has also agreed to supply power from its Ramagundam facility, according to Mr. Satheesan. NTPC has agreed to ink a power purchase agreement in this regard, he said.

Two BESS projects to be delayed

Meanwhile, the BESS projects being developed by the KSEB at Pothencode in Thiruvananthapuram district and Sreekandapuram in Kannur district are likely to be delayed. According to Mr. Satheesan, these 80 MWh projects are expected to be commissioned only by March 2027.

Originally, the KSEB had informed the State Electricity Regulatory Commission that these two projects, in addition to BESS projects at Mylatti, Areacode and Mulleria, would be ready by October 2026. Later, the deadlines were shifted towards the end of 2026.

Published – October 07, 2026 11:10 am IST



Source link

Krutika Dalvi : The Strategic Force Behind Thryve Group LLP’s Rising Influence
KLSR Infratech donates 1 lakh notebooks and pens for government schools in A.P.
Start-ups, investors, industry to meet at IIT Palakkad innovation summit
Lokayukta catches Public Prosecutor accepting bribe in Kalaburagi
Amit Shah assures church leaders that FCRA Bill will not be applied retrospectively
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

Assam polls: Congress, Raijor Dal seal seat-sharing deal

India Times Now Desk
India Times Now Desk
March 19, 2026
Karnataka’s Shivamogga Airport will get night-landing facility within 3-4 months, says KSIIDC Chairperson
Gold, silver surge on MCX as Venezuela unrest fuels safe-haven demand | Check city-wise rates
Madras High Court imposes ₹1 lakh cost on lawyer who sought to recover bypoll expenses from resigned MLAs
Walkathon marks Vigilance Awareness Week in Kalaburagi
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?