Reading: Only one of four Bengaluru suburban rail corridors clears land hurdle
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Only one of four Bengaluru suburban rail corridors clears land hurdle

India News

Only one of four Bengaluru suburban rail corridors clears land hurdle

India Times Now Desk
Last updated: August 6, 2026 8:27 am
India Times Now Desk
Published: August 6, 2026
Share
SHARE


Contents
    •  Bengaluru Suburban Rail Project (BSRP)
  • Status of the Four Corridors
  • Status
  • Non-acquisition of private land
Among the four corridors, Corridor-2 (Mallige), connecting Baiyyappanahalli and Chikkabanavara over 25.01 km, has made the most progress.

Among the four corridors, Corridor-2 (Mallige), connecting Baiyyappanahalli and Chikkabanavara over 25.01 km, has made the most progress.
| Photo Credit: File photo

More than four years after the Bengaluru Suburban Rail Project (BSRP) received approval, only one of its four corridors has completed land acquisition, while another has acquired just 7.8 acres of the required 57 acres, according to a reply by the Union government in the Lok Sabha.

The ₹15,767-crore project has incurred an expenditure of ₹2,659 crore so far, with delays attributed mainly to pending land acquisition and transfer of State government land.

Replying to an unstarred question recently by Chickballapur MP K. Sudhakar in the Lok Sabha, Union Railway Minister Ashwini Vaishnaw said that the 148.17-km BSRP is being implemented by Rail Infrastructure Development Company (Karnataka) Limited (K-RIDE), a company in which the Karnataka government holds a 51% stake. The project is funded with 20% each by the Centre and the State government, while the remaining 60% is to be raised through debt.

Among the four corridors, Corridor-2 (Mallige), connecting Baiyyappanahalli and Chikkabanavara over 25.01 km, has made the most progress. The government said land acquisition has been completed in full, separate contracts have been awarded for station buildings, and construction is under way. Tenders have also been invited for the remaining works.

 Bengaluru Suburban Rail Project (BSRP)

Total project length: 148.17 km

Project cost: ₹15,767 crore

Expenditure incurred: ₹2,659 crore

Executing agency: K-RIDE (51% owned by Karnataka Govt.)

Funding pattern: 20% Centre, 20% Karnataka Govt., 60% debt

Status of the Four Corridors

Corridor Route Current Status
Corridor-1 (Sampige) KSR Bengaluru City – Devanahalli (41.4 km) Alignment approved; land acquisition and utility shifting under way
Corridor-2 (Mallige) Baiyyappanahalli – Chikkabanavara (25.01 km) Land acquisition completed; station works in progress; tenders invited for remaining works
Corridor-3 (Parijaata) Kengeri – Whitefield (35.52 km) Alignment approved; land acquisition and utility shifting under way
Corridor-4 (Kanaka) Heelalige – Rajankunte (46.25 km) Only 7.8 acres acquired out of 57 acres required; station works started on available land

Status

For Corridor-1 (Sampige) between KSR Bengaluru city and Devanahalli (41.4 km), alignment plans have been approved, while land acquisition is under way. Shifting of signalling, telecommunication (S&T) and electrical utilities has also commenced.

A similar status was reported for Corridor-3 (Parijaata), the 35.52-km line connecting Kengeri and Whitefield. The alignment has been approved, while land acquisition and utility shifting are currently in progress.

Progress has been slowest on Corridor-4 (Kanaka), which will connect Heelalige and Rajankunte over 46.25 km. Of the 57 acres required for the corridor, only 7.8 acres have been acquired so far. However, contracts for station buildings have been awarded, and construction has begun on the land already available.

Non-acquisition of private land

The Union government said that the project has been delayed due to the non-acquisition of private land and the transfer of State government land by the Government of Karnataka. It added that regular coordination meetings are being held between K-RIDE and the Railways to resolve pending issues and expedite implementation.

While the Lok Sabha question sought revised completion timelines for the Mallige and Kanaka corridors, the government did not specify any fresh deadlines in its reply. It, however, reiterated that efforts are continuing to address land acquisition and coordination issues affecting the project’s progress.

Published – August 06, 2026 01:57 pm IST



Source link

Kakatiya-era temple razed to make way for school, draws ire of historians
Daily Quiz: On Republic Day invitees over the years
300 kg ganja seized in Thiruvananthapuram; one arrested
Kerala SIR: 11 districts record dip in voters, three show increase
Kalaburagi City Police carry out massive rowdy parade, warn habitual offenders
TAGGED:BengaluruBengaluru Suburban Rail ProjectBSRPkarnataka
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

634 drunk driving cases booked in week-long BTP drive in Bengaluru

India Times Now Desk
India Times Now Desk
March 23, 2026
NSUI holds protest outside Education Minister’s residence over NEET paper leak
MP calls for decentralisation of railway administration
AMMK gets new treasurer – The Hindu
ECI sat on vote-rigging complaint in a Maharashtra seat, says Congress
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?