Reading: Rajasthan Solar Power Curtailment: 4.3 GW Hit by Transmission Shortage
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Rajasthan Solar Power Curtailment: 4.3 GW Hit by Transmission Shortage

India News

Rajasthan Solar Power Curtailment: 4.3 GW Hit by Transmission Shortage

Times Desk
Last updated: December 14, 2025 9:26 am
Times Desk
Published: December 14, 2025
Share
SHARE


Nearly 4,300 MW of solar power capacity in Rajasthan faces complete daytime curtailment due to inadequate transmission infrastructure, putting projects worth about ₹20,000 crore at risk, industry sources said.

A total of 26 solar projects, developed by companies including Adani, ReNew, Serentica, Juniper, Zelestra, ACME and Amp Energy, are currently supplying power under the Temporary General Network Access (T-GNA) framework, as their associated transmission systems are yet to be commissioned.

With available transmission margins exhausted, power generation from these plants has been fully curtailed during daytime hours, sources said.

According to data from the Northern Regional Load Despatch Centre (NRLDC), Rajasthan has around 23 GW of commissioned renewable energy capacity, while transmission capacity stands at about 18.9 GW.

This entire transmission capacity has been allocated to projects with long-term General Network Access (GNA), leaving over 4 GW of capacity operating under T-GNA without evacuation capability.

Industry officials said that despite the commissioning of the 765 kV Khetri-Narela transmission line, only about 600 MW of additional transmission capacity became available. At the same time, over 4,300 MW was simultaneously operationalised under long-term GNA, effectively exhausting surplus margins.

In an email dated December 11, NRLDC withdrew the No Objection Certificates (NOC) for the 26 projects following the commissioning of the line and operationalisation of long-term GNA.

Also Read | Rajasthan all set for storage systems in solar energy

Developers warned that prolonged curtailment could severely impact project viability and debt servicing, and flagged the issue as a growing systemic risk as generation capacity continues to outpace transmission additions in renewable-rich States such as Rajasthan.

Industry representatives have urged the government to consider short-term relief measures, including the implementation of a Special Protection Scheme to improve evacuation under T-GNA, and the dynamic reallocation of unused GNA margins to T-GNA projects during low utilisation periods. They also called for the use of Dynamic Line Rating (DLR) to maximise real-time transmission capacity and prevent renewable assets from turning stranded.

“Most of the 4.3 GW capacity is well within its notified connectivity start date. However, due to delay in commissioning of their ATS (Associated Transmission System), they are forced to deliver power under T-GNA. There is also no formal channel through which a generator can ascertain in advance about the additional transmission capacity that will be available from commissioning of a new line,” an industry official said.

The projects facing 100% curtailment belong to multiple renewable power companies, including Adani, ReNew, Serentica, Juniper, Zelestra, ACME, and Amp Energy.

According to sources, the government had earlier said that commissioning of the 765 kV Khetri-Narela transmission line would significantly reduce 55% peak hour curtailment faced by Renewable Energy (RE) generators operating under the T-GNA arrangement.

“However, as per the latest Grid India data, after the addition of Khetri-Narela line, only 600 MW of transmission capacity has been added in the system. But the Central Transmission Utility of India operationalised 4,375 MW of capacity under long-term GNA, which exhausted the entire surplus available capacity and left almost no transmission availability for projects operating under T-GNA,” said another official with a leading RE company that operates solar projects in Rajasthan.

According to an email communication by NRLDC on December 11, the No Objection Certificate to these 26 projects has been withdrawn due to the commissioning of 765 kV Khetri-Narela D/C lines and the operationalisation of long- term GNA. “All above plants are requested not to violate the NOC in terms of Schedule or Actual,” the email said.

The officials said that with limited evacuation available and no visibility on additional transmission capacity, the 4 GW RE projects face a serious concern about project viability and debt servicing.

To avoid stranded capacity, the industry has proposed that a T-GNA-only approach can be adopted for all future RE capacity additions in Rajasthan until evacuation margins are demonstrably available, the head of a generating company said.

“Of the 23 GW operational RE capacity in Rajasthan, the transmission capacity is 18.9 GW. If this were equitably distributed among all generators, the peak hour curtailment would be only 15%, which on an annualised basis would be insignificant for all generators,” he added.

According to industry officials, the government must take immediate short-term relief measures to prevent a complete shutdown. For instance, the government can look to implement a Special Protection Scheme (SPS), which will lead to a significant improvement in capacity for evacuation under T-GNA.

SPS allows transmission corridors to operate closer to their true physical capability, as it mitigates risk from sudden outages. It thus prevents cascading failures by shedding minimal pre-identified generation only when essential, instead of pre-emptively curtailing the entire 4 GW.

They said that the government can also look at the mechanism of dynamic reallocation of unused GNA margins. During the winter season and low generation periods, there is a possibility that the capacity is not utilised fully during peak hours for RE developers with long-term GNA. The margin available from GNA should be diverted to T-GNA projects for increased evacuation corridors.

“We recommend evaluating margins using DLR principles and allowing real-time reallocation of unused GNA margins to T-GNA generators to maximise system utilisation,” said the head of the generating company.

Published – December 14, 2025 02:56 pm IST



Source link

Super 30 fame Anand Kumar launches “Super Infinity“
10 blackbucks die due to ‘bacterial infection’ in Zoological Park in Jharkhand’s Jamshedpur
CPI(M) MP moves Right to Disconnect Bill in Rajya Sabha
Will a hypothetical change in rules on women’s entry amount to ‘invasion’, Supreme Court asks in Sabarimala case
Kerala Assembly polls 2026: Pinarayi Vijayan dares Rahul Gandhi to explain how Sabarimala gold theft case accused entered Sonia Gandhi’s residence
TAGGED:India solar transmission crisisRajasthan renewable energy capacitySolar power lossT-GNA solar projectswhy solar power is curtailed Rajasthan
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News
BusinessStartup

India, Oman ink free trade agreement, labour-intensive sectors receive full tariff elimination

Times Desk
Times Desk
December 18, 2025
Panic buying of fuel continues in Belagavi
Centre tells Delhi High Court OTT accessibility guidelines for hearing, visually impaired to be finalised
SC overturns death sentence of Chennai man accused for rape and murder
Justice Nisha Banu to join Kerala High Court on December 19
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?