Reading: ₹3,000-cr 203-km Kazipet-Balharshah rail tripling works completed: South Central Railway
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » ₹3,000-cr 203-km Kazipet-Balharshah rail tripling works completed: South Central Railway

India News

₹3,000-cr 203-km Kazipet-Balharshah rail tripling works completed: South Central Railway

India Times Now Desk
Last updated: July 23, 2026 12:04 pm
India Times Now Desk
Published: July 23, 2026
Share
SHARE


Contents
  • Seamless movement on Grand Trunk route
  • A busy section
The Kazipet-Balharshah section is a crucial rail corridor linking northern and southern India.

The Kazipet-Balharshah section is a crucial rail corridor linking northern and southern India.

South Central Railway (SCR) has completed the 203-km Kazipet-Balharshah rail tripling project with the commissioning of the final 11-km stretch between Asifabad Road and Sirpur Kaghaznagar, along with electrification works and a major bridge across the Bibra River.

Seamless movement on Grand Trunk route

The ₹3,000-crore project, comprising track tripling and electrification between Kazipet and Balharshah, is expected to enhance operational efficiency and facilitate seamless movement of trains on the busy Grand Trunk route.

A busy section

The Kazipet-Balharshah section is a crucial rail corridor linking northern and southern India. It also serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years.

To decongest the route, SCR initially completed tripling works on the 33-km Raghavapuram-Mandamarri section in 2016. Subsequently, tripling and electrification of the remaining Kazipet-Balharshah stretch were sanctioned during 2015-16. The project covers 203 km, of which 159 km falls in Telangana and 44 km in Maharashtra. Since 2020, various sections of the project have been commissioned in phases.

The Kazipet-Balharshah section serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years

The Kazipet-Balharshah section serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years

According to railway officials, the entire stretch has now been commissioned except for a small portion near Balharshah station that falls under the jurisdiction of Central Railway. The pending work involves connectivity between the newly laid third line and the Balharshah yard, and work on this segment is currently in progress.

SCR General Manager Sanjay Kumar Srivastava congratulated the officials and staff involved in the successful completion of the project, according to a press release issued on Thursday (July 23, 2026).

The Kazipet-Balharshah section serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years

The Kazipet-Balharshah section serves several coal and cement sidings along the route, resulting in heavy traffic congestion and near-saturation of line capacity over the years

Published – July 23, 2026 05:34 pm IST



Source link

Women indispensable for sustainable peace, says P. Wilson at UN Peacebuilding Commission
DMK government achieved in 4 years what the AIADMK could not in a decade: Stalin
J&K L-G galvanises massive public support against drug abuse, says neighbouring country using it for terrorism, radicalisation
Farmers in Villupuram, Puducherry call for early steps to repair Sornavur anicut across Thenpennai River
Navy delegates explore natural dyeing at Sankalpa Art Village
TAGGED:grand trunk routeKazipet-Balharshah rail tripling projectrail section connecting northern and southern IndiaRailwaysTelangana train
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News
CryptocurrencyFinance ₹Investment

Prediction markets scrutiny mounts from regulators and banks

India Times Now Desk
India Times Now Desk
August 14, 2026
Congress launches revamp of U.P. organisation; focus on Jats, Gurjars, Passi, Nishad, Lodhi, forward castes
Actor Ashish Vidyarthi, wife injured in accident
India ready for ‘White Revolution 2,’ says National Dairy Development Board chairman Meenesh C. Shah
CM for speedy forest and environment clearances to PRLIS and other projects
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?