Reading: Edappally-Moothakunnam NH widening deadline extended to December
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Edappally-Moothakunnam NH widening deadline extended to December

India News

Edappally-Moothakunnam NH widening deadline extended to December

Times Desk
Last updated: May 31, 2026 6:41 pm
Times Desk
Published: May 31, 2026
Share
SHARE


Contents
  • Bridges
  • Demand for Underpasses
Around 75% of the work on the 24-km-long Edappally-Moothakunnam stretch of NH 66 is completed.

Around 75% of the work on the 24-km-long Edappally-Moothakunnam stretch of NH 66 is completed.
| Photo Credit: H. VIBHU

The National Highways Authority of India (NHAI) has set December as the revised deadline for completing the six-laning works on the 24-km-long Edappally-Moothakunnam stretch of NH 66, one of the busiest and most densely populated corridors on the highway.

Around 75% of the work on the stretch has been completed. The highway is being upgraded to enable vehicle speeds of 80 kmph to 100 kmph, NHAI sources said.

“The highway is being widened to 45 metres, including service roads, drains and allied infrastructure. Service roads will have a width of seven metres wherever land is available, to enable two-way movement of vehicles. Soil testing was carried out in May as part of the design process for the retaining walls along the corridor,” the sources said.

Bridges

While the newly constructed parallel bridge at Varapuzha was opened to traffic earlier this year, another bridge under construction at Moothakunnam is ready to be opened. The approach roads to the existing bridges along the 22-km stretch are currently being widened to ensure smoother traffic flow. Once the works are completed, the new bridges will have three lanes, while the existing bridges will continue to function with two lanes, the sources added.

Demand for Underpasses

Meanwhile, NGOs, residents’ associations and people’s representatives have renewed their demand for additional underpasses along the stretch to enable vehicles and pedestrians to cross the highway safely.

“The NHAI must construct an adequate number of underpasses as promised, since the Edappally-Moothakunnam stretch passes through densely populated areas with educational institutions and places of worship. For instance, there is no underpass along the 2.5-km stretch between Kunnumpuram Junction and the junction where NH 66 intersects the Container Road,” said Hashim Chendampilly, chairman of the NH Samyukta Samara Samithi.

He said it was high time the NHAI began work on the proposed underpass for light vehicles at Thykavu Junction, which it had promised during a stakeholders’ meeting. The junction is located roughly at the centre of the 2.5-km stretch. Underpasses are also needed at Koonammavu and Pattanam, he added.

Mr. Chendampilly said that NGOs and other groups raising the issue would not allow the remaining works to proceed unless the underpasses were constructed. He also demanded adequate drainage facilities along the highway to prevent waterlogging.

Meanwhile, the NHAI has expressed willingness to provide funds to local bodies to implement measures to prevent waterlogging along the Edappally-Kodungalloor stretch of NH 66. The move is expected to enable the smooth drainage of water from service roads to nearby waterbodies, sources said.

Published – May 31, 2026 09:16 pm IST



Source link

Telangana to host techno-cultural festival showcasing North East India from November 20
Bengaluru-bound bus catches fire: Andhra and Telangana CMs express condolences
SIR: over 50,000 hearings held in Ernakulam
India-flagged vessels start sailing out of Hormuz
Most Kochi city campuses untouched by election fever
TAGGED:NHAI sets December deadline for Edapally-Muthakunnam NH widening
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

Kerala Assembly poll: Deciphering the Malabar mandate

Times Desk
Times Desk
May 4, 2026
Pilot killed in paragliding accident in Himachal’s Bir Billing
U.S., Iran ratchet up rhetoric with peace talks in limbo
YouTuber ‘Savukku’ Shankar arrested by Chennai police
National Medical Commission sanctions 17 postgraduate seats for Alappuzha Medical College in Kerala
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?