Reading: Committee suggests ₹10-crore project to end undulations on S.A. Road
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Committee suggests ₹10-crore project to end undulations on S.A. Road

India News

Committee suggests ₹10-crore project to end undulations on S.A. Road

Times Desk
Last updated: July 11, 2026 8:04 pm
Times Desk
Published: July 11, 2026
Share
SHARE


The sinking of S.A. Road beside the Kochi metro pillars is most pronounced at Manorama Junction, where the uneven surface has been causing accidents, discomfort to commuters, and damage to vehicles.

The sinking of S.A. Road beside the Kochi metro pillars is most pronounced at Manorama Junction, where the uneven surface has been causing accidents, discomfort to commuters, and damage to vehicles.
| Photo Credit: THULASI KAKKAT

An expert committee has submitted a report to the Kerala High Court on a ₹10-crore project of the Kochi Corporation to resurface the 3.10-km long S.A. Road in the city, to do away with the gaping and frequent level differences on the fast track beside the Kochi metro pillars.

Citing the need for timely disbursal of funds for the project on S.A. Road, Mayor V.K. Minimol said such undulations on the fast track were a problem on either side of the Aluva-MG Road-Vyttila metro corridor. “Chief Minister V.D. Satheesan has been apprised of the matter, while the Kochi Corporation will shortly take it up with the Minister for Public Works,” she said.

On whether the civic agency had approached Kochi Metro Rail Limited for part funding the work along the metro corridor, she said the metro agency cited no funds for the purpose.

The metro agency had been saying that it was up to the road-owning agency to execute restoration and resurfacing works since the three-year defect liability period for resurfacing works that it executed after the metro’s commissioning was over.

However, engineers suggest a more comprehensive work on the fast track on either side of the metro corridor along not just S.A. Road, but also on M.G. Road and Banerjee Road. This would be a lasting solution to the problem, they said.

Gaping level difference

Yacub Mohan George, a former Deputy Chief Engineer of the Public Works department (PWD), attributed the differential sinking of the earth below the road strip between two adjacent pile caps to weak soil beneath. “To strengthen the earth for compacting the sub soil, sand piling, PVD [polyvinyl drain] and wooden/coconut piles can be used. Alternately, concrete land slab can be cast between the pile caps. The sinkage of the road can be reduced by sand piling, he said.

In its report submitted before the Kerala High Court, the expert committee said the gaping undulations had been caused, primarily due to the settlement of the road’s four-lane carriageway. There are locations on the road where the level difference (between the metro pile cap and the slow track’s kerb) ranges up to 300 mm, adversely affecting riding quality and safety of motorists. The proposed ₹10-crore work involves “scarifying the existing bituminous surface over a width of 4.0 m on either side of the median at affected locations, correcting the level differences with wet mix macadam of the required thickness, and the subsequently laying of dense bituminous macadam and bituminous concrete layers.”

Further, resurfacing has been proposed for the full carriageway width of 11 metres on either side of the median, to ensure a uniform riding surface. The work also includes thermoplastic road markings and the installation of reflective road studs for improved traffic safety and riding comfort. In addition, a letter has been issued to the PWD to prepare a detailed estimate and steps to rectify such undulations on roads under its jurisdiction, the report said.

Published – July 12, 2026 01:34 am IST



Source link

Measure for measure: On India’s courts and criticism
Court directs police to register case, probe Ansiba’s plaint
Penubala Harshavardhan appointed BJP SC Morcha president in Tirupati
Following the ideals of Jagjivan Ram, Congress to secure justice for downtrodden, says party leaders
KTR alleges violation of Constitution in Telangana under Congress
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

Row over ‘VIP treatment’ at Bengaluru prison: Chief Prison Superintendent transferred, two others suspended

Times Desk
Times Desk
November 10, 2025
Early snowfall brings cheer to tourists; chilly weather sets in across Kashmir
Visakhapatnam zoo summer camp to begin from May 19
PM Modi departs Johannesburg after concluding his engagements at G-20 Leaders’ Summit
Alka Yagnik breaks silence on wheelchair video after Padma Bhushan ceremony: ‘Please do not worry’ | Entertainment
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?