Reading: CMRL’s pillars over Kathipara flyover to be completed soon
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » CMRL’s pillars over Kathipara flyover to be completed soon

India News

CMRL’s pillars over Kathipara flyover to be completed soon

India Times Now Desk
Last updated: October 26, 2025 12:22 am
India Times Now Desk
Published: October 26, 2025
Share
SHARE


Contents
  • 108-ft tall pillar
  • Novel problem
  • ‘Form Traveller’

The Chennai Metro Rail’s phase II construction work over the Kathipara clover flyover is moving quickly, and will be completed in four months.

This section of Metro Rail’s Corridor 5 – Madhavaram to Sholinganallur via Alandur – has the tallest pillar and sharpest curve in the entire phase II network, said officials of the Chennai Metro Rail Limited (CMRL).

The CMRL is building six pillars at the Kathipara flyover junction.

In a few years, commuters using this corridor will have access to two stations around this junction — Butt Road and Alandur (both phase I and phase II networks integrate in this location).

108-ft tall pillar

“The construction of the second tallest pillar has been completed. While the tallest pillar, coming up at 108 feet, will be ready in November, the remaining four will be completed by the end of February,” an official said.

The CMRL began construction at the junction after receiving the Commissioner of Rail Safety’s approval, as it is being built above the operational phase I network.

Novel problem

During the construction of these pillars last month, the officials encountered a new problem. “Since a high-voltage line and the overhead electrical equipment of the phase I network were close to the upcoming pillars, electrical induction problems began to arise. This occurs when metallic structures, such as construction machinery, are in close proximity to a high-voltage line,” an official said.

“We planned the construction in such a way as to prevent electrical induction issues. But when we started work on the spans close to the Corridor 1 line, the parameters crossed the permissible limits, and as soon as we saw the signs of electrical induction, we stopped the work,” he said.

‘Form Traveller’

Officials said they immediately approached the retired chief electrical inspector of the State government to oversee the work. Based on his recommendation, the construction equipment ‘Form Traveller’ — deployed for building the balanced cantilever section — was insulated.

“Form Traveller is a movable frame that aids in constructing large spans. The overhead equipment is switched off every day once the Metro services of the phase I network stop operating, and the construction of the pillars begins. We only have four hours at night to build them, and hence, it is turning out to be a time-consuming process. The corridor 5 line over Kathipara Flyover will be completed by the end of February,” an official said.

Published – October 26, 2025 05:52 am IST



Source link

Maharashtra government orders probe into church lands
Nexus between narcotic dealers, terrorists challenge for country’s internal security: J&K L-G
Coimbatore, Tiruppur Corporations raise funds through municipal bonds
Amended wind mill repowering policy gives scope for repowering 2,000 MW of wind mills
Lionel Messi virtually unveils his 70-foot statue at Lake Town in Kolkata
TAGGED:CMRLKathibara flyoverurban square
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

Iran war impact: Pesticide industry warns of price rise, spread of fake materials

India Times Now Desk
India Times Now Desk
March 20, 2026
Brad Pitt’s romance with Ines de Ramon goes Instagram official after Angelina Jolie’s dating revelation | Hollywood
Sensex, Nifty end volatile session in green, Nifty Pharma and IT index shine, Indigo gains over 2%
Market Opening Bell: Sensex surges 550 points, Nifty near 25,300 after Trump calls off Greenland-related tariffs
8th Pay Commission: Rs 69,000 basic salary to 6% annual increment, check recommendations of draft committee
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death