By using this site, you agree to the Privacy Policy and Terms of Use.
Accept
India Times NowIndia Times NowIndia Times Now
Notification Show More
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Reading: Kakinada Gateway Port set to be commissioned by early 2027
Share
India Times NowIndia Times Now
Font ResizerAa
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
Search
  • Bharat Shreshtha Ratna Sanman
  • India News
  • Categories
    • Technology
    • Entertainment
    • The Escapist
    • Insider
    • Finance ₹
    • India News
    • Science
    • Health
Have an existing account? Sign In
Follow US

Home » Kakinada Gateway Port set to be commissioned by early 2027

India News

Kakinada Gateway Port set to be commissioned by early 2027

India Times Now Desk
Last updated: August 26, 2026 5:34 am
India Times Now Desk
Published: August 26, 2026
Share
SHARE


Contents
  • First berth
  • Connectivity
  • Legacy challenges
A view of works of the first berth of Kakinada Gateway port at Kona in Kakinada district. Photo: Arrangement

A view of works of the first berth of Kakinada Gateway port at Kona in Kakinada district. Photo: Arrangement

The Gateway port being built in the Kakinada Special Economic Zone (KSEZ) is set to be commissioned by early next year, as the construction of the above 3.3-kilometre-long breakwater facility has been completed at Kona in Kakinada district. The greenfield port will be the third port on the Kakinada coast. 

The Kakinada Gateway Port Private Limited (KGPL), a subsidiary of Auro Infra Private Limited, is building the port with an estimated cost of ₹2,620 crore, with three berths with an annual capacity of handling 16 Million Metric Ton Per Annum.

The first phase targets exporting coal, granite, fertilizers, and aluminium. A Liquefied Natural Gas terminal will be built in the second phase, facilitating maritime trade facilities for the companies engaged in oil and natural gas exploration.

A few weeks ago, the construction of the breakwater facility, 2.715 km-long South Breakwater and 589 meters of North Breakwater, was completed. 

First berth

“The construction of the first berth is in full swing and will be complete by the year-end, inching close to commissioning the port by early 2027..”, Kakinada Gateway Port Managing Director Ram Reddy Ojili told The Hindu. Spreading over 1,726 acres on the land front, the port has been blessed with a nearly six-kilometre-long coastal belt.

Connectivity

“By early next year, the ongoing works of the four-lane Bharat Mala greenfield highway, which passes through our port, will be completed, coinciding with our timeline to commission the port by then. Simultaneously, the railway authorities consented to the railway track proposed to be laid between Annavaram and the port”, claimed Mr. Ram Reddy.

The KGPL has proposed to lay the 15-km railway track, connecting its port to Samarlakota with an estimated cost of ₹400 crore. “The Kakinada district authorities are engaged in the land acquisition for the railway project”, added Mr. Ram Reddy. 

Legacy challenges

On the prospects of investment in the KSEZ, Mr. Ram Reddy has claimed; “All the legacy challenges of land have been resolved recently and talks are on with major investors for various projects”. Recently, the KSEZ authorities have handed over above 2,100 acres of land, that was excluded from the KSEZ, to the farmers.

Published – August 26, 2026 11:04 am IST



Source link

Congress leaders predict massive win in the bypoll
International Women’s Day: Shakuntala Grants launched to back women researchers and STEM education
Africans, Russians, Ukrainians among 2,089 deported from Assam since 2016
Film producers can’t cull out songs I composed for their films and sell them to music labels: Ilaiyaraaja
‘Handcuffed, dejected’: 35 people from Haryana deported by U.S.
TAGGED:Kakinada Gateway PortKakinada Gateway Port commissionedKakinada Gateway Port construction
Share This Article
Facebook Email Print
Leave a Comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Follow US

Find US on Social Medias
FacebookLike
XFollow
YoutubeSubscribe
TelegramFollow

Weekly Newsletter

Subscribe to our newsletter to get our newest articles instantly!
[mc4wp_form]
Popular News

P.J. Kurien urges Speaker to ensure Home Minister’s presence in Lok Sabha

India Times Now Desk
India Times Now Desk
August 6, 2026
Zero tolerance against terrorism is not merely India’s statement, but a Line of Action: Rajnath Singh
Bihar election: 400 Tripura State Rifles personnel to provide security
TN Rising Summit at Hosur to seal fresh investments
One dead, over 500 people affected in suspected food poisoning after temple feast in Mattanur
- Advertisement -
Ad imageAd image
Global Coronavirus Cases

Confirmed

0

Death

0

More Information:Covid-19 Statistics
© INDIA TIMES NOW 2026 . All Rights Reserved.
Welcome Back!

Sign in to your account

Username or Email Address
Password

Lost your password?